Case study 12DartfordCurtain walling

Crossways Commercial Park

Curtain walling & windows

Address
Clipper Boulevard, Dartford DA2 6QS
Our role
Specialist installation contractor (installation only)
Disciplines
Curtain walling, Windows
Package value
c. £120k
Programme
3 months
Team
6 OMFC operatives
Completed
2019

The outcome

Supplied materials managed from delivery to installation, with the full package complete in three months.

Computer-generated view of an industrial unit, with its green-framed glazed entrance.
Computer-generated view of an industrial unit, with its green-framed glazed entrance.

Overview

At Crossways Commercial Park in Dartford, OMFC installed the curtain walling and windows to a commercial building on an installation-only basis, working with materials supplied by the contractor.

Our six-person team managed the supplied materials on site, from delivery and storage through to installation, and completed the full package in three months.

Scope of works

  1. Curtain wall installation
  2. Window installation
  3. Management of supplied materials on site
  4. Six-person OMFC installation team
  5. Completed in 3 months