Case study 05LondonGlazed partitioning

100 Fetter Lane

Glazed screen partitioning

Client
Mace
Address
100 Fetter Lane, London
Our role
Specialist installation contractor
Disciplines
Glazed partitioning, Vacuum lifting
Package value
c. £200k

The outcome

Glazed screens lifted in panel by panel and handed over fully glazed, to the client’s quality standard.

The OMFC International site team lifting a glazed screen panel into position using a vacuum lifting crane.
The OMFC International site team lifting a glazed screen panel into position using a vacuum lifting crane.

Overview

This project involved the installation of a glazed screen partitioning system at 100 Fetter Lane, London, for Mace. OMFC International was engaged to install the glazed screens throughout the workspace, using specialist vacuum lifting equipment to position each panel safely and precisely.

OMFC International’s qualified installation team carried out the works from initial panel handling and crane-assisted lifting through to the final, fully glazed screen partitioning, delivering the completed installation to the client to the highest standard of quality and finish.

Scope of works

  1. Installation of glazed screen partitioning throughout the workspace.
  2. Safe handling and positioning of glazing units using specialist vacuum lifting crane equipment.
  3. Setting out and fitting of screen framing and glazing to specification.
  4. Coordination with the wider Mace site programme.
  5. Deployment of a qualified, certificated OMFC International installation team.
Next case study 06 / 17 Citibank